The 7.5-mile North Coast Rail Trail between Wilder Ranch State Park and Davenport was designed to connect a string of places along Highway 1. Most of those places opened before the trail did. Cotoni-Coast Dairies welcomed hikers in August 2025. Davenport Roadhouse marked its first year under new owners this past summer. In August 2026, the rebuilt lot above Panther and Yellowbank beaches got its ribbon cutting. Meanwhile the Santa Cruz County Regional Transportation Commission still lists the trail itself as due in fall 2026.
So the Slow Coast already works as a day out, just in the wrong order. You can reach every stop, and the path that will tie them together is still behind construction fencing. RTC asks the public to stay off the corridor until it announces the trail is finished.
The Parking Lot Was the First Thing Finished
The first part of the project anyone could use was a parking lot. The new paved lot at Panther/Yellowbank opened to the public in April 2026, before the trail was done. The Santa Cruz Sentinel covered the formal celebration on August 4. About 30 elected leaders, advocates and planners gathered at a lot that now has about 52 spaces, three accessible spaces, four motorcycle spots, bike racks, benches, a new sidewalk, wayfinding signs and a restroom.
"This is the first completed milestone of the North Coast Rail Trail project," RTC board vice chair Steve Clark said at the ceremony, according to the Sentinel. At the same event, Santa Cruz Mayor Fred Keeley announced that the lot is dedicated to Andy Schiffrin. Schiffrin has represented the 3rd District supervisor's office as an alternate on the commission for more than 50 years, and a plaque now marks the dedication.
Getting down to the sand works the same way it always has. Edible Monterey Bay describes a ravine-like goat trail down to Panther Beach that takes a little scrambling and, in the magazine's words, "keeps crowds in check."
Both Ends Were Already Running
Edible Monterey Bay's fall 2026 issue calls what is happening on the North Coast a "triple synergy": a new national monument, a new rail trail and a new era at Davenport Roadhouse. Two of those three were finished before the trail.
Cotoni-Coast Dairies is an onshore unit of the California Coastal National Monument, managed by the Bureau of Land Management. Public access started on August 16, 2025. The BLM's opening notice puts the North Trailhead at Cement Plant Road and Warrenella Road, with access from dawn to dusk and 62 parking spaces. Santa Cruz Local reported that the site has a bathroom but no overflow or street parking, so on a busy weekend the lot sets the limit on visitors. The northern network is about nine miles across three loops:
- Hawk/Káknu: a 2.5-mile loop, open to bikes and leashed dogs
- Tree/Huyya: a 1.6-mile loop plus a 1.1-mile approach, open to bikes and leashed dogs
- Wildcat/Toróma: a 3.6-mile loop plus a 2.1-mile approach, open to bikes, no dogs
The BLM's Cotoni-Coast Dairies page allows only Class 1 e-bikes and prohibits camping and overnight parking. Edible Monterey Bay reports that the ongoing build-out is expected to add about 10 miles of southern trails, along with ADA-accessible paths and pedestrian connections.
Davenport Roadhouse is the other end that was ready early. Edible Monterey Bay reports that new owners Ginny Miller, Teddy Miller and Gavin Parsons began running it in summer 2025. They redid the dining room, rebuilt the kitchen program around chef Jessie Curran, who came from State Bird Provisions, and handed the bar to Kate Palacio. Parsons told the magazine their one-year anniversary drew twice the town's population. The Roadhouse's own site lists café, lunch, dinner and a full bar from 9 a.m. to 9 p.m. every day except Wednesday, along with rooms to book. Odwalla Beach is across Highway 1, reached through a tunnel of cypress trees.
What the Trail Adds, and What Stays Separate
Once it's finished, the trail will be the spine for places that already draw their own visitors. RTC splits it into Phase I, 5.4 miles from Wilder Ranch to Panther/Yellowbank, and Phase II, 2.1 miles from Panther/Yellowbank to Davenport. Construction started in June 2024. Santa Clara-based Joseph J. Albanese Inc. is the contractor, working with the Federal Highway Administration's Central Federal Lands division.
The Davenport end is the last piece to come together. The informal coast-side parking area near town closed in early May for about six months. In its place RTC is building a formal lot, restrooms and a new pedestrian crossing of Highway 1, and coastal access at that spot is closed while the work goes on. Lookout Santa Cruz reported the closure starting May 18.
Even with the trail done, Cotoni-Coast Dairies will still be reached separately. The Sentinel reports that Phase III, a Highway 1 overpass linking the trail to the monument, is slated for construction in 2028. The Panther lot sits about 3 miles south of Cotoni-Coast Dairies.
| Piece | Status as RTC, BLM and the Sentinel describe it |
|---|---|
| Panther/Yellowbank lot | Open since April 2026, celebrated August 4, 2026 |
| Cotoni-Coast Dairies north loops | Open since August 16, 2025, dawn to dusk |
| Trail, Phases I and II | Completion estimated for fall 2026 |
| Davenport lot, restrooms, Highway 1 crossing | Under construction since May 2026 |
| Phase III overpass to Cotoni-Coast Dairies | Construction slated for 2028 |
The Sentinel puts the project's cost at about $51.4 million. Of that, $33.2 million comes from the Federal Land Access Program through the Land Trust of Santa Cruz County, $5.25 million comes from Santa Cruz County and the California Coastal Conservancy combined, and $8.2 million comes from Measure D, the transportation commission's half-cent sales tax. That leaves about $4.75 million the article does not break down. Measure D, the county's own sales tax, covers less than a sixth of the total.
The Day, South to North
Until the trail is finished, the North Coast is a drive with stops. Here they are in order heading up Highway 1 from the Westside:
- Wilder Ranch State Park. The County Bike Trail runs next to Highway 1. From it you can pick up the Enchanted Loop or the Ohlone Bluff Trail down toward Strawberry Beach. The Wilder Dairy Cultural Preserve has farmhouses, equipment barns, apple trees, chickens and goats for a self-guided tour. California State Parks lists hours as 8 a.m. to sunset and allows only service animals. Bikes are limited to 15 mph and must be walked through the ranch complex. The Park Store is closed until further notice.
- Rodoni Farms. This third-generation stand is done for the year. Its site lists produce from May through October and a 2026 pumpkin patch that ran September 26 to October 31.
- Panther and Yellowbank beaches. Park at the new lot, use the restroom, then take the goat trail down.
- Beauregard Vineyards. The tasting room is in the building that once housed Bonny Doon Vineyard's tasting room, and before that the Lost Weekend Saloon. There's a creekside lawn out back under the redwoods. Edible Monterey Bay notes that the family's history in the Santa Cruz Mountains goes back four generations. Check Beauregard's visit page before you go.
- Whale City Bakery, Bar & Grill. The bakery side is known for olallieberry croissants, artichoke bread and molasses muffins. The kitchen serves "4-Mile" burgers and calamari plates made with Stagnaro Brothers squid. Edible Monterey Bay calls the building, a former dive bar, card room and gas station, the town's "town hall, clubhouse and godsend."
- Chris Johnson Glass. This glassblowing studio and workshop is about half a mile from Whale City. Johnson told Edible Monterey Bay that Davenport is "a baby Big Sur."
- Davenport Roadhouse and Odwalla Beach. Have dinner at the bar, or cross through the cypress tunnel to the sand first. The Roadhouse serves Alta Coffee's Davenport Blend, from a family business the magazine calls a Davenport institution.
- Cotoni-Coast Dairies. Leave for the morning, before the 62-space lot fills up.
- Swanton Berry Farm and Año Nuevo. Edible Monterey Bay puts Swanton about five minutes north of Davenport and Año Nuevo State Park about 13 minutes north. The farmstand is at 25 Swanton Road.
Nearly every stop on that list will work the same way after the trail opens. What changes is the stretch between Wilder Ranch and Davenport, which becomes something you can ride. The RTC's construction updates page will post the completion announcement. For a Westside starting point, our guide to the Ingalls-Swift corridor covers the restaurants a few minutes before Highway 1 empties out.
If you split your time between the Peninsula and the coast, a weekend on the Slow Coast says a lot about how a coastal property gets used through the year. Luxury Inc. follows the Santa Cruz and coastal cities market with that seasonal rhythm in mind. Schedule a private consultation and we'll talk through which parts of this coastline fit the way you spend your weekends.